Home » Partition and Wall Framing - Installation » Fixing methods explained  

Steel Wall Systems Manual

General information/ Warranty and design considerations
Engineering design certification
Certification, standards and testing
Performance
Technical services
Fire and acoustic rated systems

Peer Steel Wall Products
Partition or wall studs and track
Deflection head and noggin track
Accessories for acoustic applications
Top hats
Plaster accessories

Partition and wall framing – installation
Bottom track fixing detail
Top (Head) track fixing detail
Top (Head) track fixing detail – suspended ceiling
Deflection head track fixing detail
Fixing methods explained
Plasterboard installation
Control joints explained
Storage and Handling
Table SWS-01 - Wall Lipped Studs
Table SWS-02 - Wall Lipped Studs
Table SWS-03 - Top Hats
Table SWS-04 - Top Hats
Design notes and sectional properties
WSL design examples
Top Hat design examples
Sectional properties SWS-05
Sectional properties SWS-06
Sectional properties SWS-07
Sectional properties SWS-08
Sectional properties SWS-09
Sectional properties SWS-10
Sectional properties SWS-11
Sectional properties SWS-12
Sectional properties SWS-13
Sectional properties SWS-14
Sectional properties SWS-15

Peer Facade System Manual

General / Design & Warranty Information
Engineering design certification
Certification, standards and testing
Performance
Technical services

Peer Façade system Products
Façade system Backing Strip
Top Hat 50, 120 and EPDM foam seal
Façade EPDM seal characteristics
Panel Layout and Top Hat spacing
Top Hat levelling and fixing – EPDM Foam seal application
Pre mark and drill boards prior to fixing
Backing Strip as a vertical spacer and sealant application
Insertion of backing strip and overlapping seal details
Backing strip overlapping seal and prep for Top board
Fixing to layer of boards and prep screw holes for filling
Finish façade joint sealing & Control Joints
Control Joints
Storage, Handling & Design Capacities
Section properties TH120
Section properties TH75 & TH50
Span table maximum wind pressure

Concealed Ceiling systems Manual

General / Design & Warranty Information
Engineering design certification
Technical services
Certification, standards and testing
Performance

PEER Concealed Ceiling Steel
Product Breakdown
Furring channel
Top cross rail
Clips
Miscellaneous components
Acoustic application accessories
Top hats
Ceiling battens
Ceiling joists
Concealed ceiling systems install
Typical suspended ceiling with TCR/FC
Direct fixing of furring channels
Drop ceiling/ceiling bulkhead
Fire rated ceilings
Acoustic STC rated ceilings
Typical concealed ceiling joists
Curven and raked ceilings
Plasterboard installation
Expansions and control joints

Design notes
Span table CCS01
Span table CCS02
Span table CCS03
Span table CCS04
Span table CCS05
Span table CCS06
Span table CCS07
Clip Capacity Table CCS08
Sectional properties SP-01
Sectional properties SP-02
Sectional properties SP-03
Sectional properties SP-04
Sectional properties SP-05

Exposed Grid system Manual

General / Design & Warranty Information
Engineering design certification
Certification, standards and testing
Technical services

PEER Exposed Grid Ceiling
Simplicitee components
Simplicitee components details
Two way exposed grid
One way linear grid
Raked ceiling detail
Light fitting detail

Installation details
Two way exposed grid
Part tile lengths/widths
Wall angle trim fixing
Suspension rod fixing
Main/Cross runner suspension clips
Main runner to wall angle junction
Detail at light fitting
Main runner to wall angle junction
Maximum load Table EGS01
Clip Capacity Table EGS-02
Grid layout examples
Ceiling tiles
Sectional properties SP-01
Previous Page
Fixing methods explained
Next Page

There are Several methods of fixing a steel wall system.

Fig 35 - example of a friction fit wall
Fig 36 - example of friction fit - plan view
Fig 37 - example of friction fit - detail

For non-load bearing partitions it is possible to install studs using the friction method to hold the studs in place in the track.
This simplifies the installation and reduces the time required.
Friction fitting keeps the studs in position until plasterboard is fastened to the studs.
Fix plasterboard to studs with plasterboard screws with screws being no more than 100 mm from tracks.

Fixing details

Friction fit
  1. Fix top and bottom tracks of partition into position.
  2. Fix first and last studs to both top and bottom tracks with screws.
  3. Insert the intermediate studs into tracks at required centres and rotate steel section into position.
  4. Check the studs are set in position and are plumb and square.
Fig 38 - example of a friction fit wall assembled
Fig 39 - mechanical fastening - detail

Fixing details

Screw Connection

An alternative to using friction fit is to use mechanical fixing methods. Studs are held in place using friction fit until fasteners can be used.

  1. Fix the top and bottom tracks into the correct position.
  2. Insert the studs into the tracks at the required centres and rotate the stud into position.
  3. Check that the studs are set plumb and square when in position.
  4. Fix all studs to both the top and bottom tracks with screws.
  5. The strength of these connections is based on pull out capacity of screws.
  6. Refer to the screw manufacturer’s recommendations for pull out capacity of screws.

Fixing details

Weld Connection
  1. Fix the top and bottom tracks in the correct position.
  2. Insert the studs into the tracks at the required centres and rotate the stud into position.
  3. Check that the studs are set plumb and square when in position.
  4. Fix all of the studs to both the top and bottom tracks with welding as per AS 1554, 1538 and 4600.
  5. After welding, all disturbed areas are to be protected from corrosion with an appropriate zinc rich primer or other surface treatment as per surface coatings supplier’s recommendations.

Nogging Track and timber Noggins used with Peer Track

Refer to figure Fig - 40 below for various
Nogging track configurations and fixing details:

Fig 40 - Timber Noggins with Peer Wall Stud Lipped
Fig 41 - Noggin Track with Peer Wall Stud Lipped

Nogging track is used to provide extra support to the stud wall.
This prevents the steel section from twisting when under load condition.
Nogging track should be fastened either with screws, rivets or welding etc to ensure firm bracing is achieved.
Refer to the maximum wall height tables SWS01 and SWS02 for the number of rows of noggings required for a particular wall height.
Nogging tracks are available in 450mm and 600mm spacing’s which can be used as a guide to ensure stud spacing’s are uniform and correct.
Other spacing’s are available on request.

Fig 42 - an example of a Peer noggin track placement in a steel wall system available in 64, 76, 92 and 150mm
  1. Place the bottom track in its position as per detail Fig 37
  2. Mark the position of the studs on the bottom tracks
  3. Place track nogging with open ends of flanges facing down on bottom track
  4. Insert the studs through the cut-outs of track noggings and into the bottom track at its position
  5. Place the top track on top of the studs
  6. Align the studs, bottom tracks, top tracks and track noggings to its required position
  7. Slide the track noggings into the correct height on studs
  8. Fasten the track noggings to both flanges of studs with either screws, rivets or welds
  9. All other stud framing works as per the above Installation detail.

Plasterboard Installation – General instruction for fixing lining to stud frame (Always follow the manufacturer’s instructions)

  1. Cut the sheets to size and then fix the sheets either vertically or horizontally.
  2. Fasten the plasterboard to each stud as shown in the figure 43 or 44.
  3. Use full sheets above and below all openings.
  4. Saw cut sheets around any openings
  5. Stagger the butt joints ensuring they do not occur on or between the same studs on opposite sides of the wall (This improves structural stability and the appearance of the decorated wall).
Fig 43 - example of Steel Stud non fire rated vertical plasterboard sheeting arrangement using adhesive/fastener combination
Fig 44 - example of Steel Stud non fire rated horizontal plasterboard sheeting using adhesive/fastener combination

Keep the bottom edge of the sheet 10mm clear of the floor.

All plasterboard installation should be in accordance with AS2588 & AS2589 and the Plasterboard manufacturer’s specifications.

Other Building Board Installations

All building board installation should be in accordance with manufacturer’s specifications and recommended installation methods.

Expansion and Control Joints

Expansion joints as well as control joints need to be provided at 12 meter maximum spacing and wherever structural expansion joints occur.

Fig 45 - non fire rated Control Joint – Steel Stud Frame and plasterboard or equivalent or cement sheeting
Fig 46 - Control Joint at intersection using Steel Studs.
Note: Control Joint should be in accordance with manufacturer’s specifications and recommendations
   PEER Industries Technical Manual Rev 05