(2) Direct Fixing of Furring Channels - Concealed Ceiling System
Refer to figs 12,13 and 14
- Locate the position of floor joists or purlins or concrete etc and based on the ceiling plan; mark the
position of the direct fix clips (Peer product code C26-80 or C26-180) on it.
- Fix the direct-fix clips C26-80 or C26-180 to the steel purlins or timber joists with two screws in shear
and to concrete with appropriate anchors.
- Connect the furring channels FC18 or FC38 to the direct-fix clip C26.
-
Check and adjust concealed ceiling system using a laser or other appropriate levelling device.
- Install ceiling board as per manufacturers specification
|
|